Follow us on Twitter Follow Us on Facebook

  DRC Home | Applicants Guide (PDF) | Submittals Checklist (PDF) |Application Form (PDF) | Agendas

Southeast Design Review Case Report

WOODHILL CENTER EAST

Back Return to Case List | Start Over | Print Report (PDF format)

Project Information

Southeast Case #  SE 2021-003

Address: 11305 Woodland Ave.
Company: City Architecture
Architect: Same as contact
Description:

Construction of new townhomes as part of Woodhill Up Next plan.

Notes:  

Committee Actions/Submissions

Date: January 5, 2021
Committee: Local Design Review Committee
Action Type: Initial Plan Submission
Conditions/Notes:  
 
Date: January 13, 2021
Committee: Local Design Review Committee
Action Type: Schematic Design Approval
Conditions:  
  • Explore the use of permeable pavers in the parking lot.
  • Better integration of the playground into the site.
  • Add pedestrian pathways to the garden.
  • Increase landscaping around the parking facing Mt. Carmel.
  • Investigate the use of a different color and material for the cladding around the dumpster that will better match the building.

 

 
Date: January 15, 2021
Committee: City Planning Commission
Action Type: Schematic Design Approval
Conditions:  

Incoporate Councilmember Slife's comments, and further consideration of drive.

Date: September 7, 2021
Committee: Local Design Review Committee
Action Type: Initial Plan Submission
Conditions/Notes:  
 
Date: September 22, 2021
Committee: Local Design Review Committee
Action Type: Approved
Conditions:  

Approved as presented.

 
Date: January 15, 2021
Committee: City Planning Commission
Action Type: Schematic Design Approval
Conditions:  
Date: September 15, 2021
Committee: Staff
Action Type: Initial Plan Submission
Conditions/Notes:  
 
Date: September 22, 2021
Committee: Local Design Review Committee
Action Type: Approved
Conditions:  
 
Date: November 5, 2021
Committee: City Planning Commission
Action Type: Approved
Conditions: