Southeast Design Review Case Report
BUCKEYE COMMONS / EMERALD ALLIANCE VI
Return to Case List | Start Over | Print Report (PDF format)
Project Information
Southeast Case # SE 2012-008
Address: | |
Company: | Cleveland Housing Network |
Architect: | Dave Abramczyk, Marous Brothers Construction |
Description: | New construct of a four story apartment building. |
Notes: | |
Committee Actions/Submissions
Date: | April 19, 2012 |
Committee: | Local Design Review Committee |
Action Type: | Initial Plan Submission |
Conditions/Notes: | |
Date: | April 25, 2012 |
Committee: | Local Design Review Committee |
Action Type: | Conceptual Approval |
Conditions: | |
The committee recommended that the architect look at the entrance canopy in regard to the tilt and its relation to the canopy over the community room. The also suggested that they consider changing the rythem of the last four window bays. |
|
Date: | May 4, 2012 |
Committee: | City Planning Commission |
Action Type: | Conceptual Approval |
Conditions: | |
Planning Commission gave conceptual approval. If the Southeast DRC approves of the final submission, the application can be approved administratively. |
Date: | May 4, 2012 |
Committee: | Local Design Review Committee |
Action Type: | Revised Plan Submission |
Conditions/Notes: | |
Date: | May 9, 2012 |
Committee: | Local Design Review Committee |
Action Type: | Approved with Conditions |
Conditions: | |
The committee approved the plans with the following conditions:
The committee also recommended that they include a small informal seating area outside for smokers and one for non smokers. |