Near West Design Review Case Report

WEST 20TH APARTMENTS

Back Return to Case List | Start Over | Print Report (PDF format)

Project Information

Near West Case #  NW 2022-013

Address: 2485 West 20th Street
Company: Geis Companies
Architect: Geis Companies
Description:

New construction apartment building off of West 25th Street

Notes:  

18 - 2 bedroom units


30 - 1 bedroom units


37 - studio units


85 total units, 85 parking spaces

Committee Actions/Submissions

Date: April 21, 2022
Committee: Staff
Action Type: Initial Plan Submission
Conditions/Notes:  

20% of units are affordable (what AMI?)

1st: Esposito, Gallagher, 

Y: Gardin, Hart, Contreras, Gallagher

N: Sandoval

 
Date: April 27, 2022
Committee: Local Design Review Committee
Action Type: Approved
Conditions:  
SCHEMATIC APPROVAL
  1. Provide greater detail to the ground floor unit entries and patio areas
  2. Provide elevations of each side of the building
  3. Detail the landscaping and lighting along West 20th and Moltke
  4. Provide additional view studies to the site, particularly the other side of the valley

Recommend:

  1. Increase the amount of balconies on Moltke

 

 
Date: May 6, 2022
Committee: City Planning Commission
Action Type: Approved with Conditions
Conditions:  

Schematic Design Approval with condition to rethink materials and fenestration. 

Date: June 2, 2022
Committee: Staff
Action Type: Revised Plan Submission
Conditions/Notes:  

1. increase screening of garage with landscaping on the West 20th frontage

Madera 1st, Hart 2nd

Y: Gardin, Madera, Hart, Gallagher, Rakauskas, Esposito, Jurca

N: Sandoval

 
Date: June 8, 2022
Committee: Local Design Review Committee
Action Type: Approved
Conditions:  
 
Date: June 17, 2022
Committee: City Planning Commission
Action Type: Approved
Conditions: