Northeast Design Review Case Report
OH PERRY ELEMENTARY SCHOOL
Return to Case List | Start Over | Print Report (PDF format)
Project Information
Northeast Case # NE 2016-009
Address: | 18400 Schenely Ave |
Company: | Cobalt Group |
Architect: | Then Design |
Description: | Seeking approval for new construction of a brick and masonry school building. |
Notes: | |
Committee Actions/Submissions
Date: | April 7, 2016 |
Committee: | Staff |
Action Type: | Initial Plan Submission |
Conditions/Notes: | |
Date: | April 12, 2016 |
Committee: | Local Design Review Committee |
Action Type: | Approved |
Conditions: | |
Voting Members Present
Project was presented by Patti Chobi (Cobalt) and Marissa Butts/Jeff Henderson (THENDesign-CEDA). Presented some basic background info on the proposed demolition before moving into the new construction. Councilman Polensek, Mary Louise Daley, and John Boksansky (NES) available for comment during the meeting.
Committee Comments, Questions, Concerns
Councilman Polensek commented that this has been a very involved process to come up with the new design and that the neighborhood has a real fondness for the school and the history that it represents. Would like to see architectural details incorporated into the new building. Would like to the design team to work with the NEORSD to look at additional stormwater controls.
Motion to approve as presented by all voting members present. Will need to return with a full landscape plan, exterior lighting, specs on any fencing treatment. |
|
Date: | May 6, 2016 |
Committee: | City Planning Commission |
Action Type: | Conceptual Approval |
Conditions: | |
Date: | May 10, 2016 |
Committee: | Staff |
Action Type: | Initial Plan Submission |
Conditions/Notes: | |
Date: | May 17, 2016 |
Committee: | Local Design Review Committee |
Action Type: | Approved |
Conditions: | |
Voting Members Present
Project presented by Hollie Dellasanti of CMSD and Jeff Henderson of CEDA/ThenDesign. Presentation focused on how the final development plan addressed the comments from the NE Design Review Committee made during the Apr 12th 2016 meeting. Additonal landscaping has been incorpoarated along the street and around the stormwater basin/community gardens. CMSD will salvage the wrought iron fencing for future use on other projects, but it will no be re-used at this site. The re-use of stonework from Longfellew school is now on hold. The future and possible redevelopment of Longfellow is now in discussions with CMSD, CRS, and the City Councilmembers. There was additional thought on how to better intergrate architectural details from the original OH Perry into the new building. Since the construction of the new school and the demolition of the original school are happening in tandem, there is difficulty in removing details and adding them into the new construction. In regards to the shadow play and the brick banding, the development plan is now showing random brick bands that will be inset about an inch to create additional shadows on the building.
Committee Comments, Questions, and Concerns
John Boksansky in attendance from Northeast Shores Development Corp. NSDC in support of the new facility.
Motion to approve with conditions to change the color of the metal sign to a more visible color against the brick facade, reconsider the alternating trees along the streetscapes, reconsider the choice of using the redbark location in a non-acidic location, reconsider the size and species of the 4" caliper trees at the service entrance, keep the emergency doors and service doors painted tan, and decide the final location of the signage when the clerestory windows are removed. (Voted 5-1) |
|
Date: | May 20, 2016 |
Committee: | City Planning Commission |
Action Type: | Approved with Conditions |
Conditions: | |
Add a few more bike racks. |