Far West Design Review Case Report
HALLE SCHOOL (BOOKER)
Return to Case List | Start Over | Print Report (PDF format)
Project Information
Far West Case # FW 2016-003
Address: | 7901 Halle Ave |
Company: | Robert P. Madison International |
Architect: | Robert P. Madison International |
Description: | Erect new Booker School at former Halle site. |
Notes: | |
Committee Actions/Submissions
Date: | January 20, 2016 |
Committee: | Staff |
Action Type: | Initial Plan Submission |
Conditions/Notes: | |
Date: | January 27, 2016 |
Committee: | Local Design Review Committee |
Action Type: | Approved with Conditions |
Conditions: | |
1. Incorporate more green area and shade on south side of building in/around area marked 'Rubber Play Surface' on site plan. Provde shade for seating area. Reconfigure fence and seating area if needed.
2. Redesign fencing around play areas to tie into the building architecture. This may be accomplished by installing masonry piers along the fence to echo the brick on the building. Cap piers with pre-cast concrete or similar. Applicant may present alternative designs that achieve the objective of tieing the fence into the building architecture. |
Date: | May 4, 2016 |
Committee: | Staff |
Action Type: | Initial Plan Submission |
Conditions/Notes: | |