Euclid Corridor Design Review Case Report
CLEVELAND FOUNDATION HEADQUARTERS - SIGNAGE
Return to Case List | Start Over | Print Report (PDF format)
Project Information
Euclid Corridor Case # EC 2022-021
Address: | 6601 Euclid Avenue |
Company: | Cleveland Foundation |
Architect: | Vocon |
Description: | New signage package for Cleveland Foundation HQ. |
Notes: | |
Committee Actions/Submissions
Date: | July 28, 2022 |
Committee: | Staff |
Action Type: | Initial Plan Submission |
Conditions/Notes: | |
1. raise concrete slightly to prevent pooling of water.
1st Mike 2nd Brown, Jerry, Trotta, Brown, Strean, Mike, Pace. |
|
Date: | August 4, 2022 |
Committee: | Staff |
Action Type: | Approved |
Conditions: | |