Euclid Corridor Design Review Case Report
UCI DEVELOPMENT | STOKES WEST
Return to Case List | Start Over | Print Report (PDF format)
Project Information
Euclid Corridor Case # EC 2022-010
Address: | NW Corner of Cedar & Stokes |
Company: | LDA architects |
Architect: | LDA architects |
Description: | |
Notes: | |
Committee Actions/Submissions
Date: | March 24, 2022 |
Committee: | Staff |
Action Type: | Initial Plan Submission |
Conditions/Notes: | |
Date: | March 31, 2022 |
Committee: | Local Design Review Committee |
Action Type: | Approved with Conditions |
Conditions: | |
1) Study grass bumpouts with the larger trees at entry; possibly reduce or adjust them for safety / visibility 2) Bike storage - design these areas and integrate with language from building and adjacent exterior spaces 3) Explore the opportunity for patios and green wall on first level townhome units (buffer space) 4) Explore bikd path or bike lanes related to alternate transportation modes and connection to existing neighborhood infrastructure 5) Study corner at Cedar & E 107 to alleviate a 'back of house' feel 6) Develop green space on Cedar and Stokes for next meeting 7) Develop the exterior mateial pallet and integrate into renderings 8) Note - investigate ways to improve crosswalks (off Carnegie onto Wilbur) by coordianting with city |
|
Date: | April 1, 2022 |
Committee: | City Planning Commission |
Action Type: | Tabled |
Conditions: | |
Date: | May 12, 2022 |
Committee: | Staff |
Action Type: | Revised Plan Submission |
Conditions/Notes: | |
Date: | May 19, 2022 |
Committee: | Local Design Review Committee |
Action Type: | Approved with Conditions |
Conditions: | |
1) Further study landscaped space near corner of Cedar & E 107th 2) Consider the exterior ceiling of third floor regarding material color for greater warmth and contrast to add interest to building |
|
Date: | May 20, 2022 |
Committee: | City Planning Commission |
Action Type: | Tabled |
Conditions: | |
The Planning Commission granted this project Schematic Design Approval on July 1, 2022. |
Date: | August 11, 2022 |
Committee: | Staff |
Action Type: | Revised Plan Submission |
Conditions/Notes: | |
1st Pace, 2nd Holland A: Strean, Solon, Pace, Holland, Brown, Augoustidis, Rothenberg. |
|
Date: | August 19, 2022 |
Committee: | Local Design Review Committee |
Action Type: | Approved |
Conditions: | |
|
|
Date: | August 19, 2022 |
Committee: | City Planning Commission |
Action Type: | Approved with Conditions |
Conditions: | |
Approved incorporating the DRAC's comments. |
Date: | April 27, 2023 |
Committee: | Staff |
Action Type: | Revised Plan Submission |
Conditions/Notes: | |
Tabled by CPC on May 5, 2023. |
|
Date: | May 4, 2023 |
Committee: | Local Design Review Committee |
Action Type: | Schematic Design Approval |
Conditions: | |
Concerns & Comments: 1) Clarify function of new space between the two townhome buildings in landscape plan updates. 2) Add some treatment on the wall, just right of entry door on building rear, to add visual interest. 3) Main building seems like a large & monolithic structure, and a significant departure from previous iteration. 4) Address section of building over front entryway so that, with window sizes and parapet height, it reads differently ( e.g. increase window sizes, different material, more glass) so that the building can read as two separate volumes (more similar to previous design). 5) The main building is a solid extrusion, from floor to top, occassionally changing colors. The fenestration and articulation of the building's size feels incompete, e.g. the balconies appear to be a system just hanging off of flat surfaces. 6) Compilation & assembly of materials feels patched. 7) Insure that landscape design in public realm is well designed and treated, not just mowed lawn. 8) Insure proper screening of electrical equipment near the corner of Stokes & Cedar. 9) Return with complete lighting plan. 10) Material on building ends appearnot to enhance the quality of the building.
Motion - Wagner / Second - Pace Rothernberg Y Brown Y Herring N Holland Y Madison Y Pace Y Strean Y Trotta Y Wagner Y Non-voting present: Scott, Provolt |
Date: | May 11, 2023 |
Committee: | Staff |
Action Type: | Revised Plan Submission |
Conditions/Notes: | |
Date: | May 18, 2023 |
Committee: | Local Design Review Committee |
Action Type: | No Action Taken |
Conditions: | |
After a very thorough discussion of this project, there was no action taken because the initial motion for approval with conditions introduced did not have the mojority members' approval (3 yeas, 5 nays, 1 abstension). A subsequent motion to disapprove was not introduced. The conditions stated were:
Committee members present: Rothenberg, Augoustidis, Brown, Herring, Holland, Madison, Strean, Trotta, Sargeant
Non-voting members present: Scott, Provolt, Yablonski, Tzeng |
|
Date: | May 19, 2023 |
Committee: | City Planning Commission |
Action Type: | Approved with Conditions |
Conditions: | |
Final material palette to return to staff.
|