Euclid Corridor Design Review Case Report
E 90TH APARTMENTS
Return to Case List | Start Over | Print Report (PDF format)
Project Information
Euclid Corridor Case # EC 2022-003
Address: | 1839 E 90th Street |
Company: | Geis Companies |
Architect: | GLSD / Geis Companies |
Description: | |
Notes: | |
Committee Actions/Submissions
Date: | January 13, 2022 |
Committee: | Staff |
Action Type: | Initial Plan Submission |
Conditions/Notes: | |
Date: | January 20, 2022 |
Committee: | Local Design Review Committee |
Action Type: | Schematic Design Approval |
Conditions: | |
1) Insure that details & renderings are accurate. 2) Consider grading front slope of lawn up to meet finsh grade. 3) Consider change in material application where Hardie board meets the ground for durability. 4) Consider color selection (seems heavy). 5) The dark color around the bay window sections highlight the assymetry of the windows. |
|
Date: | January 21, 2022 |
Committee: | City Planning Commission |
Action Type: | Schematic Design Approval |
Conditions: | |
Conditions: Incorporate the DRAC's comments and work more with neighborhood. |
Date: | May 26, 2022 |
Committee: | Staff |
Action Type: | Revised Plan Submission |
Conditions/Notes: | |
Date: | June 2, 2022 |
Committee: | Local Design Review Committee |
Action Type: | Approved with Conditions |
Conditions: | |
Consider or explore extending the black Hardie Material down to the floor of the 2nd floor to aligh with the other material changes.
Non-voting members in attendance: Karis Tzeng, MidTown Cleveland
This project is in Ward 7. |
|
Date: | June 3, 2022 |
Committee: | City Planning Commission |
Action Type: | Approved with Conditions |
Conditions: | |
Extend black handle material down to the floor of the 2nd floor to align with the other material changes. Work with staff on final facade details. |