Euclid Corridor Design Review Case Report
FORMER MPC PLATING FACILITY DEMOLITION
Return to Case List | Start Over | Print Report (PDF format)
Project Information
Euclid Corridor Case # EC 2021-034
Address: | 1859 E 63rd Street |
Company: | HZW Environmental Consultants, LLC |
Architect: | B&B Wrecking |
Description: | |
Notes: | |
Committee Actions/Submissions
Date: | December 13, 2021 |
Committee: | Staff |
Action Type: | Initial Plan Submission |
Conditions/Notes: | |
Date: | December 16, 2021 |
Committee: | HDRS |
Action Type: | Approved |
Conditions: | |
Please note: although Kim Scott's name is checked as present, Marka Fields facilitated this meeting and was present in place of Kim Scott. |
|
Date: | December 17, 2021 |
Committee: | City Planning Commission |
Action Type: | Approved |
Conditions: | |
All four buildings approved for demolition. |