Euclid Corridor Case #  EC 2021-021

Address: Chester & Stokes, Reserve Court
Company: Midwest Development Partners
Architect: Baker Engineering & Site Design Group
Description:
Notes:  

Committee Actions/Submissions

Date: August 10, 2021
Committee: Staff
Action Type: Initial Plan Submission
Conditions/Notes:  
 
Date: August 19, 2021
Committee: Local Design Review Committee
Action Type: Approved
Conditions:  

Final approval for design development for Chester & western portion of Reserve Court streetscape infrastructure plan.

Schematic approval for the entire project's streetscape development.

The remainder of project including materials, signage, furnishings, landscape materials, public art  and details will be subject to further review.

 

 
Date: August 20, 2021
Committee: City Planning Commission
Action Type: Schematic Design Approval
Conditions:  

1) Schematic Design Approval for the complete presentation (continue to work with the City); 2) Final Approval for Phase 1 (streets in green on map) and the western portion of Reserve Court. Applicant to return for review of other items.