Euclid Corridor Design Review Case Report
PARKING STUCTURE SUPPORTING 10600 CHESTER AVE.
Return to Case List | Start Over | Print Report (PDF format)
Project Information
Euclid Corridor Case # EC 2020-007
Address: | 10590 Chester, between Chester & Reserve Court |
Company: | FitzGerald |
Architect: | FitzGerald / Power Construction |
Description: | |
Notes: | |
Committee Actions/Submissions
Date: | February 27, 2020 |
Committee: | Staff |
Action Type: | Initial Plan Submission |
Conditions/Notes: | |
Date: | March 5, 2020 |
Committee: | Local Design Review Committee |
Action Type: | Approved with Conditions |
Conditions: | |
1) provide complete elevations of the exterior facades. |
|
Date: | March 6, 2020 |
Committee: | City Planning Commission |
Action Type: | Conceptual Approval |
Conditions: | |
Additional elevations are needed. |
Date: | August 25, 2020 |
Committee: | Staff |
Action Type: | Revised Plan Submission |
Conditions/Notes: | |
Date: | September 3, 2020 |
Committee: | Local Design Review Committee |
Action Type: | Schematic Approval W/Conditions |
Conditions: | |
Provide details of parking garage's south facade and show materials proposed for temporary treatment (approximately 2 years). |
|
Date: | September 4, 2020 |
Committee: | City Planning Commission |
Action Type: | Schematic Design Approval |
Conditions: | |
Explore how gargage faces the public ROWs. |
Date: | October 7, 2021 |
Committee: | Staff |
Action Type: | Revised Plan Submission |
Conditions/Notes: | |
Date: | October 14, 2021 |
Committee: | Local Design Review Committee |
Action Type: | Approved |
Conditions: | |
Date: | November 19, 2021 |
Committee: | City Planning Commission |
Action Type: | Approved |
Conditions: | |