Euclid Corridor Design Review Case Report
MALTZ PERFORMING ARTS CENTER DEMOLITION
 Return to Case List | Start Over
         | Print Report   (PDF format)
 Return to Case List | Start Over
         | Print Report   (PDF format)
Project Information
Euclid Corridor Case # EC 2018-046
| Address: | 1855 Ansel Road | 
| Company: | |
| Architect: | |
| Description: | |
| Notes: | |
Committee Actions/Submissions
| Date: | December 13, 2018 | 
| Committee: | Staff | 
| Action Type: | Initial Plan Submission | 
| Conditions/Notes: | |
| Date: | December 20, 2018 | 
| Committee: | Local Design Review Committee | 
| Action Type: | Approved | 
| Conditions: | |
| Date: | December 21, 2018 | 
| Committee: | City Planning Commission | 
| Action Type: | Approved | 
| Conditions: | |

