Project Information
Euclid Corridor Case # EC 2016-042
Address: | 1891 E 93rd Street |
Company: | Cleveland Clinic |
Architect: | Westlake Reed Leskosky |
Description: | |
Notes: | |
Committee Actions/Submissions
Date: | January 18, 2017 |
Committee: | Staff |
Action Type: | Initial Plan Submission |
Conditions/Notes: | |
Date: | February 2, 2017 |
Committee: | Local Design Review Committee |
Action Type: | Schematic Design Approval |
Conditions: | |
Additional non-voting members in attendance: Anthony Whitfield, Daniel DeAngelo, Michael McBride, Dionne Broadus Conditions: 1) Study height of ribbon window 2) Study potential of additional windows on E 97th to accommodate internal non-patient areas (e.g. lounges, offices) 3) Study a reduced size of patient waiting area |
|
Date: | February 3, 2017 |
Committee: | City Planning Commission |
Action Type: | Approved |
Conditions: | |
Schematic Design Approval. |
Date: | February 13, 2017 |
Committee: | Staff |
Action Type: | Revised Plan Submission |
Conditions/Notes: | |
Date: | February 16, 2017 |
Committee: | Local Design Review Committee |
Action Type: | Approved with Conditions |
Conditions: | |
Building placement is approved (final), which will allow the permitting of the building foundation. The building's exterior design has been approved by the EC Committee and requires approval of the Planning Commission. The following items will return to the Euclid Corridor Committee for approval before being reviewed by the Planning Commission for final approval: 1) Provide landscape plan and plant materials schedule 2) Provide finalized materials selection (building shell and windows system) 3) Provide information for site furnishings (benches, trash recepticles, bike racks) 4) Provide lighting plan with product information 5) Provide signage plan |
Date: | April 13, 2017 |
Committee: | Staff |
Action Type: | Revised Plan Submission |
Conditions/Notes: | |
This revised plan represents a phased future development, which includes a building addition without a specific timeline. The current approval is for the main building only with the understanding that final approval will require the following:
|
|
Date: | April 20, 2017 |
Committee: | Local Design Review Committee |
Action Type: | Schematic Design Approval |
Conditions: | |
This revised plan represents a phased future development, which includes a building addition without a specific timeline. The current approval is for the main building only with the understanding that final approval will require the following:
|
Date: | May 10, 2017 |
Committee: | Staff |
Action Type: | Revised Plan Submission |
Conditions/Notes: | |
Date: | May 18, 2017 |
Committee: | Local Design Review Committee |
Action Type: | Approved |
Conditions: | |
The revised presentation addresses the issues raised from previous meeting on 4/20/17.
There should be a supported effort to study a median extension since this newly developed area will experience a high volume of pedestrian traffic between the Health Education Bldg and the Dental School Bldg on Chester between E 93rd & E 97th. |
|
Date: | May 19, 2017 |
Committee: | City Planning Commission |
Action Type: | Approved with Conditions |
Conditions: | |
Approved with Condition that applicant incorporate the DRAC's comments and that applicant will include some suggestions for treatment of pedestrian crossings. |