Project Information
Euclid Corridor Case # EC 2016-027
Address: | 11501 Mayfield Road |
Company: | RDL Architects |
Architect: | RDL Architects |
Description: | |
Notes: | |
Committee Actions/Submissions
Date: | September 7, 2016 |
Committee: | Staff |
Action Type: | Initial Plan Submission |
Conditions/Notes: | |
Committee wanted designer to consider 1) bronze color pallatte with same concept of gradiant scheme 2) using panels continuously instead of partial to create more contituity 3) address cornices of building to create greater visual prominance for the first floor
Applicant will plan to return on October 6th. |
|
Date: | September 15, 2016 |
Committee: | Local Design Review Committee |
Action Type: | Tabled |
Conditions: | |
Date: | October 13, 2016 |
Committee: | Staff |
Action Type: | Revised Plan Submission |
Conditions/Notes: | |
Comments were that there didn't seem to be rationale between the building vocabulary and the addition. The diagonal lines seemed arbitrary and random. The look is cluttered and it needs to be more organized. |
|
Date: | October 20, 2016 |
Committee: | Local Design Review Committee |
Action Type: | Tabled |
Conditions: | |
Date: | November 3, 2016 |
Committee: | Staff |
Action Type: | Revised Plan Submission |
Conditions/Notes: | |
Date: | November 17, 2016 |
Committee: | Local Design Review Committee |
Action Type: | Approved |
Conditions: | |