Euclid Corridor Design Review Case Report

LINK 59 CAMPUS MASTER PLAN

Back Return to Case List | Start Over | Print Report (PDF format)

Project Information

Euclid Corridor Case #  EC 2015-034

Address: E 57th through E 63rd Streets, between Chester & Euclid Avenues
Company: Geis Companies (GLSD Architects)
Architect: GLSD Architects & Geis Construction, Geis Companies
Description:
Notes:  

Committee Actions/Submissions

Date: September 24, 2015
Committee: Staff
Action Type: Initial Plan Submission
Conditions/Notes:  
 
Date: October 1, 2015
Committee: Local Design Review Committee
Action Type: Conceptual Approval
Conditions:  

Conditions:

1) Provide more welcoming campus entryways from Chester & Euclid by reducing the distinct 45 degree angle of each corner.

2) Provide additional trees in parking lot interiors.

3) Include landscape treatments along all other campus streets (E 57th, E 61st & E 63rd)

4) Insure that landscape requirements are met via city code campuswide.

5) Define building heights/massing (possible higher density) in future layout.

6) Insure developer provides a more detailed master plan updates as project progresses (including higher density, future parking needs, lighting, sign placement, etc.)

 

 
Date: October 2, 2015
Committee: City Planning Commission
Action Type: Conceptual Approval
Conditions:  

With best efforts to meet DRAC's comments.

Date: March 23, 2016
Committee: Staff
Action Type: Revised Plan Submission
Conditions/Notes:  
 
Date: March 31, 2016
Committee: Local Design Review Committee
Action Type: Approved with Conditions
Conditions:  

Recognizing the evolving nature of master plans, the plan approval was limited to the following:

1) Only approval of building placement & location of buildings 1-4

2) Approval of E 59th Street infrastructure that provides access to buildings 1-4

3) Approval of any infrastructure in the public right-of-way on E 59th Street and connecting to buildings 1-4

 
Date: April 1, 2016
Committee: City Planning Commission
Action Type: Approved
Conditions: