Follow us on Twitter Follow Us on Facebook

  DRC Home | Applicants Guide (PDF) | Submittals Checklist (PDF) |Application Form (PDF) | Agendas

Euclid Corridor Design Review Case Report

LINK 59

Back Return to Case List | Start Over | Print Report (PDF format)

Project Information

Euclid Corridor Case #  EC 2015-026

Address: E 59th Street between Chester & Euclid
Company: Geis Companies
Architect: GLSD Architects ^ Geis Construction
Description:

Construct a one-story, 18,600 sf building built speculatively for a maximum of 5 tenants.

Notes:  

Committee Actions/Submissions

Date: August 26, 2015
Committee: Staff
Action Type: Initial Plan Submission
Conditions/Notes:  

Main concerns: 1) building orientation appears to intend to serve the future UH development and not necessarily residents of the area as the presentation implies. 2) conceptual placement/massing of bldg 3 could act as a buffer from residential/pedestrian traffic from north of Chester Ave. 3)Applicant should deliniate which site work is being proposed to be completed within the scope of the first building development, particularly as it relates to the suburban style parking lot(s).

 
Date: September 3, 2015
Committee: Local Design Review Committee
Action Type: Conceptual Approval
Conditions:  
 
Date: September 4, 2015
Committee: City Planning Commission
Action Type: Conceptual Approval
Conditions:  
Date: September 27, 2016
Committee: Staff
Action Type: Revised Plan Submission
Conditions/Notes:  
 
Date: October 6, 2016
Committee: Local Design Review Committee
Action Type: Approved with Conditions
Conditions:  

1) Signage will be presented separately as the graphics presented need a hierarchy.

2) Building cornices will be further studied for modifications.

3) Applicant will return with landscape plan, lighting plan and roof plan.

 
Date: October 7, 2016
Committee: City Planning Commission
Action Type: Approved
Conditions:  

Schematic Design Approval.

Date: January 11, 2017
Committee: Staff
Action Type: Revised Plan Submission
Conditions/Notes:  
 
Date: January 19, 2017
Committee: Local Design Review Committee
Action Type: Approved with Conditions
Conditions:  

Any decorative treatment regarding signage and graphics on the building will require separate review and approval.

 
Date: January 20, 2017
Committee: City Planning Commission
Action Type: Approved
Conditions: