Euclid Corridor Design Review Case Report
STEPSTONE ACADEMY CLASSROOM BUILDING
Return to Case List | Start Over | Print Report (PDF format)
Project Information
Euclid Corridor Case # EC 2015-020
Address: | 3328 Carnegie Ave. |
Company: | Mark Fremont Architects |
Architect: | Mark Fremont Architect |
Description: | |
Notes: | |
Committee Actions/Submissions
Date: | July 30, 2015 |
Committee: | Staff |
Action Type: | Initial Plan Submission |
Conditions/Notes: | |
Date: | August 6, 2015 |
Committee: | Local Design Review Committee |
Action Type: | Approved with Conditions |
Conditions: | |
1) Will provide staff a comprehensive plan for trash removal (location and screening of dumpsters) 2) Study the Cedar Ave. frontage so that it includes landscape materials 3) Insure that mechanical equipment is minimally visible from the street |
|
Date: | August 7, 2015 |
Committee: | City Planning Commission |
Action Type: | Approved with Conditions |
Conditions: | |
Approved incoporating the DRAC's conditions. |