Project Information

Euclid Corridor Case #  EC 2013-007

Address: Rapid & Bus Transit Stations - Cedar Road
Company: City Architecture
Architect: City Architecture / McTech Corp
Description:
Notes:  

Committee Actions/Submissions

Date: February 28, 2013
Committee: Local Design Review Committee
Action Type: Initial Plan Submission
Conditions/Notes:  
 
Date: February 28, 2013
Committee: Local Design Review Committee
Action Type: Approved with Conditions
Conditions:  

Approval of the proposed updates on the west side of the station, with the condition that 1) the applicant further study the canopy dimensions for better coverage of passenger areas and share findings with the Committee; 2) the applicant will return for Committee to review revised plans with the updates on the east side of the station, including lighting fixtures, canopy structures & locations, landscape plantings, and the railing system.

Date: March 14, 2013
Committee: Local Design Review Committee
Action Type: Revised Plan Submission
Conditions/Notes:  
 
Date: March 14, 2013
Committee: Local Design Review Committee
Action Type: Approved
Conditions:  
 
Date: March 15, 2013
Committee: City Planning Commission
Action Type: Approved
Conditions: