East Design Review Case Report
PROJECT BORON
Return to Case List | Start Over | Print Report (PDF format)
Project Information
East Case # EAST 2021-023
Address: | 2777 E 75th Street |
Company: | Weston, Inc. |
Architect: | GMA Architects / Arco National |
Description: | |
Notes: | |
Committee Actions/Submissions
Date: | November 17, 2021 |
Committee: | Staff |
Action Type: | Initial Plan Submission |
Conditions/Notes: | |
The Planning Commission granted the project Schematic Design Approval on December 3rd, 2021. |
|
Date: | November 23, 2021 |
Committee: | Local Design Review Committee |
Action Type: | Schematic Approval W/Conditions |
Conditions: | |
Site Plan - 1) Show connectivity between the Red Line & Blue Line transit stations to the employee door. · 2) That connectivity should show existing and/or proposed sidewalks within right of ways around the building. · 3) The sidewalks connecting from the right of way to the employee door as well as sidewalks from onsite parking to door(s). · 4) Consideration: move the building closer to the OC right of way (within 50 feet). · 5) Add considerably more landscape material to screen parking lot, enhance the office area and on the building façade. Materials should include a mix of large groupings of evergreens, deciduous shrubs and trees, and organized in a more natural pattern to bring down the scale of the building. · 6) Eliminate rain garden on E 75th and replace it with mounding and plantings in a more naturalized arrangement; there and along the northern half of the loading dock area. Architecture · 7) Consider painting an accent color that compliments the building color and ties into the office section of the building. · 8) Consider the opportunity to add brighter colors to the office portion of the building. · 9) Revise or reorient the spacing of the windows on the office section. Consider adding spandrel glass to infill blank space on office section for a more complete & cohesive look.
Signage will be reviewed separately. Two additional voting members were in attendance, not reflected on the meeting motion form: Dawn Glasco and Marlane Weslian, who both both voted to approve the project. A
|
Date: | December 14, 2021 |
Committee: | Local Design Review Committee |
Action Type: | Revised Plan Submission |
Conditions/Notes: | |
Date: | December 14, 2021 |
Committee: | Local Design Review Committee |
Action Type: | Approved with Conditions |
Conditions: | |
Plsaceholder. |
|
Date: | December 17, 2021 |
Committee: | City Planning Commission |
Action Type: | Approved |
Conditions: | |
CPC approved a revised site plan on March 4, 2022, with the stipulation that landscape plan return to staff. |