WOODLAND CENTRAL GREEN INFRASTRUCTURE PROJECT
Return to Case List | Start Over | Print Report (PDF format)
Project Information
East Case # EAST 2017-002
Address: | Kinsman Road, south of Woodland |
Company: | Northeast Ohio Regional Sewer District |
Architect: | Ch2M Hill, Human Nature |
Description: |
The Northeast Ohio Regional Sewer District (Sewer District) plans to construct a green infrastructure project in the Central neighborhood as part of its combined sewer overflow (CSO) control program called Project Clean Lake. The proposed project consists of two project areas: the West Basin and the East Basin. The Basin subject to review by the East Design Review Committee is the West Basin. |
Notes: | |
Committee Actions/Submissions
Date: | January 17, 2017 |
Committee: | Staff |
Action Type: | Initial Plan Submission |
Conditions/Notes: | |
Date: | January 24, 2017 |
Committee: | Local Design Review Committee |
Action Type: | Approved |
Conditions: | |
Motion to approve the project with the consideration of the following comments: 1). Inclusion of historical signage of the site 2). Signage or secondary connections facing towards Grand Avenue 3). Access point curb-cut (former street), is to be reduced to 15’-20’ wide. The area in front of the bollards is to be a concrete section, stained brick red in color. Also, concrete formations should flank the side of the drive, to provide seating elements and prevent cars from driving into the site 4). Applicant to study supplemental lighting options, which could be included in the future
|
|
Date: | February 3, 2017 |
Committee: | City Planning Commission |
Action Type: | Approved |
Conditions: | |