Follow us on Twitter Follow Us on Facebook

  DRC Home | Applicants Guide (PDF) | Submittals Checklist (PDF) |Application Form (PDF) | Agendas

Downtown/Flats Design Review Case Report

PROGRESSIVE FIELD ADMINISTRATIVE BUILDING (VERTICAL EXPANSION)

Back Return to Case List | Start Over | Print Report (PDF format)

Project Information

Downtown/Flats Case #  DF 2023-019

Address: 2401 Ontario Street
Company: Mody Nolanm Inc
Architect: Same as contact
Description:
Notes:  

Committee Actions/Submissions

Date: March 29, 2023
Committee: Local Design Review Committee
Action Type: Initial Plan Submission
Conditions/Notes:  
 
Date: April 6, 2023
Committee: Local Design Review Committee
Action Type: No Action Taken
Conditions:  

Postponed untill the next meeting.  The committee asked that the applicant add arcitecetural features to denote the entry and study bringing back the barrel vault.

Date: July 6, 2023
Committee: Local Design Review Committee
Action Type: Revised Plan Submission
Conditions/Notes:  
 
Date: July 6, 2023
Committee: Local Design Review Committee
Action Type: Approved with Conditions
Conditions:  

Approved with conditions that they study the limestone extending to the top on the 4 corners of the building and the equipment screening extending around the stairwell.