Project Information
Downtown/Flats Case # DF 2014-069
Address: | 1710 Prospect Avenue |
Company: | Perspectus Architecture |
Architect: | Perspectus Architecture |
Description: | Complete building demolition of existing Mad Hatter building. New building is a two-story, 29,000SF facillty with a one story connection back to the existing Harbor Light Complex. Site will also include a new trash enclosure, transformer, emergency transformer and 77 parking spaces. The parking access will be gated with direct entry from E. 18th Street and E. 16th Place. |
Notes: | |
Case is not closed because as of August 20, 2014, we have not reviewed the proposed site plan and elevations for Final Approval. |
Committee Actions/Submissions
Date: | July 28, 2014 |
Committee: | Staff |
Action Type: | Initial Plan Submission |
Conditions/Notes: | |
Date: | July 31, 2014 |
Committee: | Local Design Review Committee |
Action Type: | Approved |
Conditions: | |
Applicant must return to DRAC to show treatment of the demolition site if no new construction is to begin within six months. |
|
Date: | August 1, 2014 |
Committee: | City Planning Commission |
Action Type: | Approved |
Conditions: | |
Date: | January 30, 2015 |
Committee: | Staff |
Action Type: | Initial Plan Submission |
Conditions/Notes: | |
Date: | February 5, 2015 |
Committee: | Local Design Review Committee |
Action Type: | Approved |
Conditions: | |
Requirement to have City Planning staff approve lighting and verification of front wall security entrance. |
|
Date: | February 6, 2015 |
Committee: | City Planning Commission |
Action Type: | Approved |
Conditions: | |