Downtown/Flats Design Review Case Report
FIRST ENERGY STADIUM HVAC CHILLER
Return to Case List | Start Over
| Print Report (PDF format)
Project Information
Downtown/Flats Case # DF 2014-064
| Address: | 100 Alfred Lerner Way |
| Company: | GPD Group |
| Architect: | GPD Group |
| Description: | Stadium addition of new HVAC chiller and piping system to existing radio telecommunication rooms in existing service level of stadium. |
| Notes: | |
Committee Actions/Submissions
| Date: | June 10, 2014 |
| Committee: | Staff |
| Action Type: | Initial Plan Submission |
| Conditions/Notes: | |
We had to wait for Architecture to approve it per Interim Director Rybka's request. |
|
| Date: | July 2, 2014 |
| Committee: | Staff |
| Action Type: | Administrative Approval |
| Conditions: | |