Downtown/Flats Design Review Case Report
FIRST ENERGY STADIUM HVAC CHILLER
Return to Case List | Start Over | Print Report (PDF format)
Project Information
Downtown/Flats Case # DF 2014-064
Address: | 100 Alfred Lerner Way |
Company: | GPD Group |
Architect: | GPD Group |
Description: | Stadium addition of new HVAC chiller and piping system to existing radio telecommunication rooms in existing service level of stadium. |
Notes: | |
Committee Actions/Submissions
Date: | June 10, 2014 |
Committee: | Staff |
Action Type: | Initial Plan Submission |
Conditions/Notes: | |
We had to wait for Architecture to approve it per Interim Director Rybka's request. |
|
Date: | July 2, 2014 |
Committee: | Staff |
Action Type: | Administrative Approval |
Conditions: | |