Follow us on Twitter Follow Us on Facebook

  DRC Home | Applicants Guide (PDF) | Submittals Checklist (PDF) |Application Form (PDF) | Agendas

Downtown/Flats Design Review Case Report

FLATS EAST BANK PHASE II BUILDING 4

Back Return to Case List | Start Over | Print Report (PDF format)

Project Information

Downtown/Flats Case #  DF 2014-001

Address: Old River Road in the Flats
Company: Metro Consulting
Architect:
Description:

Permit application for the building approved July 18, 2014.

Notes:  

Elelvations approved at conceptual approval stage. Final Approval held back until lighting, signage, landscaping, and streetscape elements are brought back.

Committee Actions/Submissions

Date: April 3, 2014
Committee: Staff
Action Type: Revised Plan Submission
Conditions/Notes:  
 
Date: April 3, 2014
Committee: Local Design Review Committee
Action Type: Conceptual Approval
Conditions:  

Motion for conceptual approval. Special consideration needed for panels over storefront, above the canopy. Applicant will return for signage, lighting, landscaping & streetscape.

 
Date: April 4, 2014
Committee: City Planning Commission
Action Type: Approved with Conditions
Conditions:  

Incoporating the DRAC's comments. Project to return for Final Approval.

Date: March 12, 2015
Committee: Staff
Action Type: Initial Plan Submission
Conditions/Notes:  
 
Date: March 19, 2015
Committee: Local Design Review Committee
Action Type: Approved with Conditions
Conditions:  

-committee suggested to review the stroke size on the bottom lettering portion of the sign. 

 
Date: March 20, 2015
Committee: City Planning Commission
Action Type: Approved with Conditions
Conditions:  

Incorporating the DRAC's comments.

Date: April 2, 2015
Committee: Staff
Action Type: Revised Plan Submission
Conditions/Notes:  

All street amenities and lighting plan (CPP) will be coming for final approval.

Signage and patio for each storefront owner will be submitting seperatly 

 
Date: April 9, 2015
Committee: Local Design Review Committee
Action Type: Approved with Conditions
Conditions:  

-Approved the overall design.

Conditions: Return with infrastructure detail for both the streetscape and landscaping (proposed raised curbs, depth of trenches); clearly render the public spaces in the site plan indicating what is developer responsibility and private tenant responsibility; provide sustainability details as to how the permeable pavers will be maintained and how snow removal will occur.

 
Date: April 17, 2015
Committee: City Planning Commission
Action Type: Approved with Conditions
Conditions:  

Approved incorporating the DRAC's comments.

 

Note: this project was Tabled by CPC on April 10, 2015.