AT&T EQUIPMENT ROOM UPGRADE AT FIRST ENERGY STADIUM

Back Return to Case List | Start Over | Print Report (PDF format)

Project Information

Downtown/Flats Case #  DF 2013-031

Address: 100 Alfred Lerner Way
Company: Ed Block, PE
Architect: Ed Block PE, Architect
Description:

Upgrade/alteration to existing AT&T equipment room at service level of Cleveland Browns Football Stadium. Equipment room expanded to accomodate additional equipment with upgrades to existing HVAC and electrical systems. Additional work shall include the mounting of two (2) telecommunications antennas to exterior of the stadium.

Notes:  

Committee Actions/Submissions

Date: April 19, 2013
Committee: Staff
Action Type: Initial Plan Submission
Conditions/Notes:  
 
Date: April 19, 2013
Committee: Staff
Action Type: Administrative Approval
Conditions: