Downtown/Flats Design Review Case Report
CUYAHOGA COUNTY HEADQUARTERS AND TOWER ON 9TH COMPLEX
Return to Case List | Start Over | Print Report (PDF format)
Project Information
Downtown/Flats Case # DF 2013-007
Address: | 2079 AND 2017 East 9th Street |
Company: | Geis Construction |
Architect: | Geis Construction |
Description: | New construction for an 8-story office building for the Cuyahoga County headquarters. |
Notes: | |
Approval of building but not the plaza on May 13, 2013. |
Committee Actions/Submissions
Date: | February 12, 2013 |
Committee: | Staff |
Action Type: | Initial Plan Submission |
Conditions/Notes: | |
Date: | February 15, 2013 |
Committee: | Staff |
Action Type: | Tabled |
Conditions: | |
Sent to Planning Commission for Informational Purposes Only. No action taken. |
Date: | March 26, 2013 |
Committee: | Staff |
Action Type: | Initial Plan Submission |
Conditions/Notes: | |
Date: | February 28, 2013 |
Committee: | Local Design Review Committee |
Action Type: | Approved with Conditions |
Conditions: | |
Three motions: 1) Approve building demolitions as presented. 2) Approve proposed building footprint contingent on 18 in. protection zone be provided on north side of building. 3) Conceptual Approval of building design with condition that entrance identity be considered from all directions. Recommend security issues be thoroughly discussed at next meeting. |
|
Date: | March 1, 2013 |
Committee: | City Planning Commission |
Action Type: | Approved with Conditions |
Conditions: | |
Approve subject to DRAC's comments. |
Date: | April 3, 2013 |
Committee: | Staff |
Action Type: | Revised Plan Submission |
Conditions/Notes: | |
Date: | April 4, 2013 |
Committee: | Local Design Review Committee |
Action Type: | Approved with Conditions |
Conditions: | |
Increase size of logo at top of building. |
|
Date: | April 5, 2013 |
Committee: | City Planning Commission |
Action Type: | Approved |
Conditions: | |