Follow us on Twitter Follow Us on Facebook

  DRC Home | Applicants Guide (PDF) | Submittals Checklist (PDF) |Application Form (PDF) | Agendas

Downtown/Flats Design Review Case Report

NEW SUBSTATION FOR CPP

Back Return to Case List | Start Over | Print Report (PDF format)

Project Information

Downtown/Flats Case #  DF 2011-091

Address: 4901 S. Marginal Road
Company: Middough Inc.
Architect: Middough Inc./Cook Paving & Construction
Description:

Construct a new substation for Cleveland Public Power. Includes foundations for transformers, grounding grid, security fence.

Notes:  

Approve with condition that screening designated on attached sheet "Enlarged Entrance Plan" be performed by June 2012.


Another set of plans signed off on on March 5th, 2012. Same conditions.

Committee Actions/Submissions

Date: November 28, 2011
Committee: Staff
Action Type: Initial Plan Submission
Conditions/Notes:  
 
Date: December 23, 2011
Committee: Staff
Action Type: Administrative Approval
Conditions:  

That screening designated on attached sheet "Enlarged Entrance Plan" be performed by June 2012.